Now, suppose you have identified activities on the critical path and need to give them extra protection. In this case, you would provide a higher

click to enlarge
cost buffer to these activities than other activities which are not on the critical path. It is common for the critical path of a project to changes during the course of a project. Therefore,
it’s safer to pad high risk activities for cost over-run, regardless of whether they are on the critical path or not. For example, you might be developing a non-critical component for a client. If the contract specifies fixed time, then you may want to put extra cost buffer to ensure
schedule crashing, if required, is possible. Alternatively, you may want to pad all activities by 10% and the high-risk activities by 20%.
Reserve Analysis is not done in isolation to determine the project budget. To read about other techniques, read the Techniques for Determining a Project Cost Budget article.