Rescheduling a task is often a necessary step when things are delayed.
During this (and other instances), Office Project 2007 can reschedule any remaining work (based on tasks you select) after a specific date. To have Office Project 2007 reschedule incomplete work, follow these steps:
- Select a task to update in the Gantt Chart.
- Choose Tools, choose Tracking, and choose Update Project.
- In the Update Project dialog box, select the Reschedule Uncompleted Work To Start After option and then select a date from the drop-down list. See the above figure.
- Click OK.
You can also reschedule work for multiple tasks at the same time. To do this, use the CTRL key to select noncontiguous tasks or use the Shift key to select contiguous ones. Then, select the Update Work As Complete Through option and choose a date from the drop-down list.
After this is done, the tasks are split