PM Certification and Scope Management

Written by:  • Edited by: Michele McDonough
Published Aug 20, 2009
• Related Guides: Project Management Institute | Stakeholder Analysis

There are some tools and techniques defined by the Project Management Institute (PMI) that can help you manage scope more effectively. In this article, we'll explore what’s new in Project Scope Management as per the fourth version of the Project Management Body of Knowledge (PMBOK).

Comparison of Version 3 and Version 4 – Project Scope Management

The diagram shows a comparison of the two versions. As you can see, not a lot has changed in terms of processes. T

V3V4Comparison
click to enlarge
he erstwhile Scope Planning process has been replaced with Collect Requirements. Notice that all processes now start with a verb. For the CAPM and PMP exams, it is important for you to recall the names of the processes as specified in the PMBOK. In other words, Scope Definition is not the same as Define Scope.

For a review of the Define Scope, Create WBS, Verify Scope and Control Scope processes, read A Summary of PMBOK Practices - Scope Management.

In this article, we’ll dive deeper into the new process Collect Requirements.

Collect Requirements

Collect Requirements is the new process in the Project Scope Management process group. This process includes gathering and documenting stakeholder needs and expectations. In addition, the process involves documenting project and product features and functions. To be successful in collecting stakeholder requirements, you must have tremendous facilitation skills to extract precise information.

Vague requirements is a common reason for project failure. Therefore, it is critical for you to implement the Collect Requirements process accurately. The output of this process sets the foundation for cost, schedule, and quality planning. Since this is one of the most crucial processes, in many organizations the role of collecting requirements is called Business Analyst or Business Consultant. It is a highly specialised role. In an Agile team, the Product Owner is usually responsible for collecting requirements. However, the ScrumMaster is expected to participate. In such a setup, the person responsible for collecting requirements will usually not participate actively in other processes, such as scheduling.

New Scope Management Inputs, Tools and Techniques, and Outputs (ITTOs)

CollectRequirements ITTO
click to enlarge
The diagram displays the ITTOs related to Collect Requirements. Follows is a brief overview of each new ITTO:

Input

Stakeholder Register: Is an input that relates to collating details, such as expectations, influence, and constraints, about each project stakeholder. Stakeholder Analysis helps you create the Stakeholder Register. If the wrong stakeholders are identified, the requirements gathered will be inaccurate. This is another common reason for project failure.

Tools and Techniques

  • Group Creativity Techniques: Can include a litany of techniques, such as Delphi technique (Leverages experts), brainstorming, and nominal group technique (brainstorming with voting).
  • Group Decision Making Techniques: Can include techniques, such as unanimity and dictatorship.

Outputs

  • Requirements Documentation: Contains all the requirements of the stakeholders as per the defined business needs.
  • Requirements Traceability Matrix: Helps in tracing back to the original requirements. For example, you may have created a set of features. Through the Requirements Traceability Matrix, you can trace the features back to the original requirements. It is very rare to have a one-to-one mapping of features to requirements. Usually several features will map to one requirement.The Requirements Traceability Matrix is useful to show stakeholders that what you will deliver is directly linked to addressing the requirements and hence the business needs.
  • Requirements Management Plan: This is created instead of the erstwhile Scope Management plan (a PMBOK version 3 artifact). This plan shows how the requirements will be gathered, analyzed, and managed during the project.

 