
click to enlarge
When you enter your optimistic, expected, and pessimistic durations into the
PERT Entry form, you can change how much weight you apply to each one. For example, maybe you want to apply more weight to the optimistic view--everything's looking really good for your project. You can change the duration weights, but keep in mind the three numbers must add up to 6. So, if you increase the optimistic option to 2, you must likewise decrease one of the other durations. Click on the icon that looks like a set of scales to access this function.
What if your expected task duration is 4 days, your pessimistic estimate is 6, and your optimistic estimate is 2. Project is calculating 4--times 4, because it gives it four times more weight to expected duration--and then it adds in one 6 and one 2, and divides it all by 6. So you have 16+2+6 = 24 divided by 6 is 4. Let's look at changing each estimate: Your optimistic view is weighted 2, (2+2); expected is weighted 3 (4+4+4); pessimistic is weighted 1 (6) for a total of 22 divided by 6 = 3.66 days. You're better off letting Project use its default weights, but I wanted you to see how it works.