click to enlarge
As you can see, not only are tasks that are linked to Task 100 affected, but also many other changes can be seen, including
summary task durations and the start and finish dates of many tasks.
Being able to see your changes as they occur without having to continuously scan the project file can be a real time-saver as you analyze your project plan and implement changes.
Even though the Change Highlighting feature presents a nice reminder of the interrelatedness of many tasks in your project, it is only a temporary visual clue. As soon as you save the project file or make another change, the original change highlighting is removed and often replaced with a new set of change data.
If you don't want to see changes appear in blue, you can turn off Change Highlighting altogether. To do that, follow these steps:
- Choose View.
- Choose Hide Change Highlighting.