As you probably well know, tasks are not always performed in chronological order based on their placement in the Task Sheet in Project. So, how do you know which tasks need to get done this week?
There is the "Who Does What When" report, but I've always found it easier to color code my tasks right there in Gantt Chart view. Here's how you get to such a display:
- Choose View: More Views from the Menu bar
- Select Gantt Chart in the Views list and click Copy. . .
- Enter a Name (i.e., Date Color Code View)
- Next to Filter, click the drop-down arrow and choose "Date Range"
- Click the checkbox next to "Highlight filter" to enable it
- Click OK
All that's left to do is to apply your new view. When you do, you'll be asked to select a start and finish date for your task range. When the Gantt Chart displays, you'll see the tasks that fall within your selected range highlighted in blue.
These steps helps you create a custom project view which is not to be confused with Project 2007's new Change Highlighting feature that highlights the domino effect one seemingly small change can have on your entire project.