
click to enlarge
The default probabilities included in Project 2007 for the likelihood of the optimistic, most likely, and pessimistic estimates are, in order, 1 out of 6, 4 out of 6, and 1 out of 6. This is why, when you use the PERT Formula you divide the sum of the optimistic estimate, the most likely(4) and the pessimistic estimate by six.
To use the default probabilities in Project to calculate estimated duration, click on the "View" toolbar and select "PERT Analysis." After you do this, select the PERT Entry Sheet and enter in the estimates for pessimistic, optimistic, and most likely. Then, click Estimate PERT. Project 2007 will then perform the PERT Formula calculation. You can now also view Gantt charts corresponding with the optimistic, pessimistic, and most likely scenarios.