The turbine support structure can be in the form of a monopile which is pile-driven into the seabed, a steel jacket structure which is fixed to the seabed using steel piles or suction pads, or a floating support to which the turbine is fixed.
Monopile
This is a single circular parallel column fabricated from 60mm thick steel plates which have been formed in a rolling mill. These rolled sections are butt-welded together around their circumference to make a steel tube which can be 70 meters in length or longer depending on the depth of water.
Once fabricated it then has a numerous sacrificial anode blocks welded to the structure below the waterline.
The monopile is shot blasted and primed with zinc paint, coated with anti-corrosive paint and then epoxy is splattered onto the structure. This extends from the bottom up to the area required for fitting the transition piece, this being given a few coats of zinc paint only. It is then ready for transportation to the wind farm location.
Transition Piece
This is fabricated in the same manner as the monopile and it contains a maintenance platform. The transmission piece has a larger internal diameter than that of the monopile which enables it to slip over the monopile. Once it is in the correct position the transition piece is welded to the monopile.
Installation of the Monopile
The monopile is lifted off the transportation barge by an adjacent jack-up crane and lowered vertically until it is on the seabed.
A hydraulically or air operated pile driver hammer is then attached to the monopile and this hammers the monopile into the bedrock.
The transmission piece is then fitted and welded, the area around the joint being fully corrosion proofed.
Some offshore contractors use a different method of installation by drilling a hole in the seabed into which the monopile is fitted. After installing the monopile into the hole, the gap between the monopile and the hole is grouted using pressurized concrete. This method has the advantage that the monopile can be installed complete with the transition piece.
Fabrication and Installation of a Steel Jacket Support.
This has been extensively covered in my previous article entitled Offshore Oil and Gas Platforms, so I will just give a brief description of installation method.
The steel jacket is transported offshore lying horizontally on the barge deck.
The jacket contains integral water and fuel oil tanks in the legs and these are used as ballast tanks, additional temporary ballast tanks being welded onto the legs to assist installation.
Once on location the jacket is floated of the barge, de-ballasted to the near vertical position then further de-ballasted, lowering it onto the seabed. Steel piles are driven through guides at the bottom of the legs right down into the bedrock and grouted using concrete. A transition piece is welded to the structure to facilitate the fitting of the nacelle tower.
The steel jacket support is then ready for the wind turbine nacelle to be attached.