Conducting a boiler performance test can be for understanding the current level of performance of the boiler, for any trouble shooting of the boiler for performance deviations, and for proving the performance guarantees. These entire three requirements can be met by the procedure adopted for performance guarantee testing. Before starting the performance guarantee test we have to understand the contact requirement fully, understand fully the performance level of the boiler, keep in mind the normal areas of concern, decide the right time for the test, organize the test instruments, make sure all local measurement grid points are in order, install all test instruments at the specified areas, do a trial test, and declare the guarantee test.
Understand the contact requirement
- Understand all guarantees well including those agreed including added any after contract finalization
- Talk to performance designer as to whether he has taken any calculated risk during the proposal
- Look at the penalty for each guarantee and be clear about the severity levels
- Be clear on the demonstration guarantee - what each means
- Look at rejection clauses in the contract
- Study the performance guarantee proposal submitted and approved
Understand fully the performance level of the boiler
- Make sure you have log readings of each load under which guarantees are agreed
- Evaluate the performance of the boiler and correct it to design fuel
- Be sure you are using the contracted and approved code for PG test
- Make sure you are evaluating all unaccounted losses and check how far you are eating into the manufacturers margin
- If required, inform the site of the findings from log data and ask them to retune and give another set of data
The normal areas of concern
- Oxygen and flue gas temperature at boiler outlet - only single point measurement for regular log reading
- Do a grid measurement during commissioning and check whether the point is close to the average grid value for the all loads guarantee is made
- Coal sampling and testing - total moisture evaluation is very critical and has to be done as per procedure in the standard being followed
- Power consumption readings - Equipment agreed to be included and current, voltage and power factor readings to be taken
- Percentage combustibles measurement in bottom ash - fly ash normally no problem faced
Decide the right time for the test
- Make sure the ambient conditions are conducive for PG test - avoid rainy season
- Complete the performance evaluation of the boiler and make sure the guarantees are met with correction to design conditions as per contracted code
- Decide test team - it is a good practice to have a performance engineer in the team if the boiler is first of its kind
- Make out clear responsibility for each team member - never exceed five (four in the team is good) excluding the performance engineer
- Evolve strategy for achieving the guarantee if there is any concern in any area
Test instruments
- Make sure all instruments planned to be used have valid calibration certificate and from a third agency of repute
- The multi point measurement probes for temperature and flue gas sampling are made ready and are as per standard
- All the thermocouples must be individually calibrated and should be within the expiration of calibration period
- Flue gas analysis equipment for oxygen, carbon-dioxide, and pollutants like NOx and SOx must be calibrated with calibration gases provided by supplier
- The flue gas measurement by Orsat must also be organized - leakage of air into flue gas during sampling is a major concern. All efforts to avoid this should be taken by checking and rechecking
Local measurement grid points
- Location of grid is very important as in a large duct there will be high amount of imbalance and stratification
- Care must be taken while providing the grid tapping points for proper access to insert the long probes
- Avoid tapping points near a direction change, void region, or near the tapping point hole
- The number of points for grid must be as per code used for PG test
- The power consumption measurement points and connections must be identified and connection procedure ensured