Heavy Lifting Using Hydraulic Jacks – Installing a Boiler Drum

Written by:  • Edited by: Lamar Stonecypher
Updated Apr 4, 2010

Boiler drum is one of the heaviest part of a boiler in a power plant. Installation of the boiler drum by hydraulic jacks is explained in this article.

Boiler Drum.

The most critical part of the boiler in a thermal power plant, Boiler drum functions mainly as the feeding point for the water and separating point between water and steam.

In a typical 600 MW thermal power plant, the drum weighs around 300 Tons. The drum itself is a cylindrical vessel of diameter 1.8 meters,12 meters long, 125 mm thick with dished ends and is made of carbon or alloy steel.

The important point for installation apart from the weight is its location. It is located at a height of around 85 meters, high up in the boiler and hung from the top of the boiler structure.

Installation.

Drum lifting is a milestone in boiler erection that signals the completion of the boiler structure installation.

For the installation of this heavy part following issues require special consideration.

  • Installation of a heavy weight at a high position requires special attention to safety in all aspects of the operation.
  • The boiler structure is already in place to support the weight which means there is restricted access for using heavy cranes near to the lifting point.
  • Interference with the structures already in position, require that during part of the lifting the drum is in an inclined position.

Drum lifting was in the earlier days done using winches and pulley blocks. As the unit sizes and drum weights increased, drum lifting using jacks became the preferred method.

Strand Jack.

Using Strand Jacks has become the convenient method of lifting a boiler drum all over the world. Multiple strands in two or more strand jacks slowly but surely lifts the drum to its position. This is a simple method to lift the heavy weight.

Except for the preparation phase, only one or two operators are required for lifting the drum. Multiple strand jacks offer redundancy, reliability and safety. Using Strand Jacks is easier to install than a winch system and less costly than using a very heavy crane.

The Strand Jack is located on temporary beams on top of the boiler structure above the final position of the drum. Two or four jacks are used based on the lifting arrangement. Lateral movements of the jacks are possible by mounting them on roller skids. This is necessary to maintain verticality and to avoid interference with the supporting structure.

Strands

The jacks itself uses multiple strands, 10 to 14 depending on the load and jack capacity. The lower ends of the strands connect to blocks that fix one end of the strands. The other end of the strands is free and moves through the jack. The blocks connect to the lifting lugs of the drum by links or grommets.

The strands are made of high strength special steels.

Lifting

The lifting operation takes around 8 to 12 hours. The drum lifts off directly from the transportation vehicle. Lifting the drum at an incline is necessary to avoid interference with the supporting structures.The multiple jacks can operate in synchronization or separately. This allows for safe lifting evn if the drum is at an incline. Once it reaches the final position the permanent supports are installed.

The attached figures show the steps in a typical boiler drum installation.

The multiple strands and the positive locking method of the jacks give redundancy, reliability and safety for the entire operation.

Images

(untitled)(untitled)(untitled)

Comments

Showing all 11 comments
 
johnzactruba Nov 8, 2010 6:20 PM
reply Shrikant G
the asfe operating parctice is to bring down the drum and change the sling. ( the cost and time is significantly lower than a a catastrophic failure)
Shrikant G Nov 6, 2010 3:01 AM
Drum lifting
sir
In 300 MW Unit, while lifting the drum ( at 16 mtr level ) if one of wire rope / pulley may found damage , then is it possibble to delift the drum from 12 mtr to 0 level.with same rope.or hang it for few time at same location ???????? clarify ....!
johnzactruba Nov 1, 2010 10:01 AM
reply shrikant
Normally drum is transported using a Cometto a multi axle trailer that can jack up and down. This it is very easy to unload. Other wise you have to use a crane of sufficient capacity. Another method is to jack down using jacks and suitable supports.
shrikant Nov 1, 2010 3:17 AM
Drum unloading
sir
i want to know , how to unload drum from trailer to ground.
by crane or ??????. Plz mention capacity of crane if so
dhinesh Jun 2, 2010 8:34 AM
thanks
thanks sir.it graves some Idea about Strand Jack
johnzactruba May 28, 2010 8:21 AM
reply dinesh
pls visit the below link
http://www.fagioli.it/?pag=39&lang=ENG
dhinesh May 27, 2010 11:53 PM
need more details about Strand Jack.
hello sir,
i need more details .I'm working in power plant.so i would like to know the internal structure of Strand Jack.could u help me!
Anonymous May 10, 2010 3:13 AM
reply
Very good one.....
johnzactruba Apr 5, 2010 4:33 AM
reply arunrajav
Yes. You will require some temporary steel for support. This could be a very simple beam to support the jacks if lifting is straight , or it could be more complicated if the inclined drum lifting and horizontal movements in both directions are required.
Arun Raja Apr 4, 2010 9:28 PM
structures
sir,
Thank you for this article, iam having one doubt for lifting the drum shall we provide an temporary structural arrangement
kavi Jan 22, 2010 10:14 PM
RE: Heavy Lifting Using Hydraulic Jacks – Installing a Boiler Drum
this artical is very well written...
 
blog comments powered by Disqus
Email to a friend