What is Boiler Hydrostatic Test?

Written by:  • Edited by: Lamar Stonecypher
Updated Nov 24, 2009

The boiler in a modern Thermal Power Plant produces steam at very high pressures and temperatures. One of the most important yet simple test that ensures the integrity of the boiler is the ‘Hydrostatic Test’. What is it? How is it done?

A string of catastrophic failures marked the starting era of the steam engine. The boiler explosion in the Grover Shoe Factory in Brockton, Massachusetts on March 10, 1905 triggered the implementation of the boiler safety rules. Today, stringent regulations control the boiler design, materials, manufacture and operation. These are mandatory as per law all over the world.

In a large Thermal Power Plant there are about Ten Thousand tons of steel tubes, pipes, drums and other vessels that contain the high pressure steam. More than Sixty Thousand weld joints make the Boiler an integrated vessel to produce steam. Design calculations, metallurgical inspections and manufacturing inspections assure the integrity of every part and every weld joint. Hydrostatic test is the last of the test to ensure completion , compliance and safety before the boiler produces steam.

The test consists of filling the Boiler with water and pressurizing the water to at least one and half times the maximum operating pressure for a short time. Every part is subject to more than the maximum stress it will normally encounter. This is an endurance test; any weak link fails during the test.

Why water?

Why do we use water as the media for a hydrostatic test ? Water is the most easily available liquid. There are no environmental or toxic issues. There is another important reason. It is the compressibility or rather the incompressibility of water. Water is almost incompressible. For carrying out the hydrostatic test in large power plant boiler we require around 600 cubic metre of water. Since water is almost incompressible, to increase the pressure form atmospheric to 250 bar we require only an additional amount of one cubic meter of water. This is faster and requires much less effort. In case of the failure of any part the pressure also is reduced immediately preventing further damage.

Test Requirements

Ensure that all work is completed and documented. Connect a high pressure positive displacement pump (Hydrostatic pump) to the boiler. Fix a calibrated and accurate pressure gauge to the boiler. All valves and opening in the boiler are closed. Fill the boiler with water using a high capacity filling pump. During filing ensure removal of entrapped air by opening vents at the highest point in the boiler. Entrapped air will drastically increase the time taken to reach the test pressure.

Running the hydrostatic test pump increases the boiler pressure gradually till the test pressure. Normally the test pressure is is 1.5 times the maximum allowable operating pressure. Close the pump discharge valves to lock the system pressure. The pressure in the boiler should maintain without dropping for at least 30 minutes. Bring down the pressure to the normal operating pressure and visually inspect for any signs leakages or wetting of the surfaces. Depending on the size and capacity of the boiler this may take a few hours. After the inspection reduce the pressure gradually to atmospheric and drain the boiler.

Test is witnessed by inspection agencies or regulatory authorities, who then approves and certifies the test.

Mandatory Hydrostatic tests done annually by regulatory authorities are a check on material degradation and ensure the continuous safety of the boiler. Hydrostatic tests are not only for boilers.

Use the same methods to test any pressure vessel or piping that stores or transports pressurised media. This is a simple but very important test which all mechanical and process engineers should know about.


Comments

Showing all 65 comments
 
muhammed saeed Sep 23, 2011 6:57 AM
test protocal of hyduralic test of steam turbine
what is hyduralic test of reaction type back pressure steam turbine
johnzactruba Aug 7, 2011 8:10 PM
reply : Quantity of DM water reqd for a Boiler of 600 MW power plant.
For 600 mw the water required is around 1000 cubic Meters.
Anjesh Aug 2, 2011 8:06 AM
Quantity of DM water reqd for a Boiler of 600 MW power plant.
Dear sir,
Pl tell me,what is the water quantity required for Hydro test of boiler in 600 MW power plant.
johnzactruba Feb 24, 2011 9:22 AM
reply U S SAHAY
5 bar / minute with hold points every 50 bar is normally practised. Same should be followed for depressurizing also.
U S SAHAY Feb 24, 2011 5:47 AM
BOILER HYDRAULIC TEST
WHAT SHOULD BE RATE OF RISE OF PRESSURE AND RATE OF DEPRESSURISING FOT HIGH PRESSUR BOILER
Yasir Jan 8, 2011 1:16 AM
Boiler hydrotest
why hydrotest conduct at 1.5times of working steam pressure?
ayman Dec 29, 2010 3:19 PM
hydro test
sir the hydrotest for all boiler (econmoizer-drum-water wall -superheater coils)
if that correct it's not dangerous on superheater coil because it's not design to carry water
chinmoy sen Dec 21, 2010 10:08 AM
thermal power plant
why Rh outlet pressure is low than Rh inlet pressure?
Manikandan sigamani Dec 19, 2010 7:28 PM
Differential expansion of steam turbine
dear sir,
how to reduce the LP turbine differential expansion. in out 135 MW turbine differential expansion reaches the alarm value. we keeping the reheater temperature low (510 deg C) to reduce LP differential expansion, please give some suggestion.
johnzactruba Dec 17, 2010 10:21 PM
reply amol
ppm of what Sodium ? Silica ?
amol Dec 16, 2010 11:56 PM
hydro test
sir
i wud lyk to know the how much ppm of water normaly use for hydro test.
2-if ppm is less than procedure ,what will be the its effect?
Imran Khan Dec 4, 2010 5:52 AM
Hydro test
Sir , Why Hydro test is carried out only 1.5 times of Design Pr. , why not other valve .
2. For Chemical Cleaning we are doing only for eco / evaporator , but for Super heater DM water Flushing , for Reheater no any chemical cleaning Why ?
johnzactruba Nov 24, 2010 4:44 PM
reply DURGA PRASAD PADHY
For an ideal gas if the volume changes from 1 to 0.5 the pressure wil increase from 1 to 2.
In the case of water the volume change is only 1.5 % . After that it is almost like a solid.
DURGA PRASAD PADHY Nov 22, 2010 4:27 AM
Hydro test
In one of your answer u told -Water is not incompressible, it is almost incompressible, maybe about 1 %. tThis property is used for the hydro test. So the additional water required for increasing pressure is only around 1 to 1.5 % of the volume. Th pump is only adding this additional quantity of water into the same volume increasing the pressure. So as long as there is no leak .

In this answer you have mentioned water is incompressible,maybe about 1%.What is represents as 1%?Kindly reply in detail.
johnzactruba Nov 13, 2010 7:22 AM
reply DURGA PRASAD PADHY
Hydro Test is done to bring out any latent defect in the material or manufacturing process. There may be some defect that will not show up at 1 times the working pressure during the test. But can show itself after along operaion period. Hence test is done at 1.5 times.
DURGA PRASAD PADHY Nov 13, 2010 4:08 AM
RE: What is Boiler Hydrostatic Test?
SIR WHY HYDROTEST IS DONE FOR 1.5 TIMES THE WORKING PRESSURE?
ashish Vyawhare Oct 26, 2010 12:30 AM
hydro test
How to do the hydro test for reheater tubes?
johnzactruba Oct 9, 2010 10:01 PM
reply deepak
There is really no modern addition to hydro testing.
deepak Oct 9, 2010 10:25 AM
boiler hydro test
dera sir,

kindly explain the most modern method of conducting boiler HT.
johnzactruba Oct 2, 2010 10:12 AM
reply Manikandan sigamani
Water is not incompressible, it is almost incompressible, maybe about 1 %. tThis property is used for the hydro test. So the additional water required for increasing pressure is only around 1 to 1.5 % of the volume. Th pump is only adding this additional quantity of water into the same volume increasing the pressure. So as long as there is no leak .
Manikandan sigamani Oct 1, 2010 6:07 AM
hydro test
dear sir, water is not a compressible liquid, then how can we pressurize the tubes during hydro test?
Manikandan sigamani Sep 30, 2010 5:10 AM
Pressure holding during hydro test.
Dear sir,
Water is non-compressible liquid. during hydro test ,Pressure is raised to 150% of rated pressure through the Boiler feed water pump.since the water is non- compressible liquid how it can hold the pressure after closing of discharge valve of pump. Closing dicharge valve of pump means , we are reducing the force on water. please explain me.
Mohammed Kashif Sep 23, 2010 5:30 PM
RE: What is Boiler Hydrostatic Test?
why hydrotest preesure is 1.5 times of working pressure?
H J Chaudhari Sep 2, 2010 11:18 AM
Hydraulic test of Boiler RH system.
Is there any problem to RH tubings/coils/pipings to take hydraulic test 1.5 times the working pressure.we are not taking hydro test after annual overhaul of boiler and RH system only checked by vacuum.we are observing first BTF in RH system within month period.is this due to micro leakages can not be detected during vacuum test.What will be the solution as per your opinion.
johnzactruba Aug 25, 2010 11:22 AM
reply T N TRUEMAN
Normally hydro test is done at 1. 5 times the working pressure. Pressure is held at this point for half hour. After this the pressure is reduced to less than working pressure and held for sufficient time for carrying out the inspection. There is no requirement for hold the pressure fo36 hrs.
T N TRUEMAN Aug 25, 2010 7:19 AM
pressure holding hrs.
sir, we done the hydraulic test of our boiler. our boiler working pr. is 122 kg/sq.cm. we hold the pressure 80 kg/sq.cm aorund 36 hrs. is it correct? please explain.
johnzactruba Aug 11, 2010 6:19 PM
reply RAJAPANDIAN
1. Level of the drum is only the indication of the difference in water qty entering and the steam qunatity leaving. It will not affect the pressure.
2. When the presuure lifts the safety valve the steam escapes through the valve. This flow of steam also applies a pressure to the spring. So for the valve to close the force required is the pressure + velocity force. That is why the valve seats at a lower pressure. Normally called " blowdown " this should seat within 3 % to 5 %v of the lifting presure. This ac be adjusted by the blowdown rings.
3. Using sprays will affect the efficiency since the water is bypassing the normal thermal circuit, there is no heat addition to this water.
RAJAPANDIAN Aug 11, 2010 12:26 PM
DRUM PRESSURE
DEAR SIR,
1. WHEN BOILER DRUM LEVEL IS GOING HIGH,THEN WHAT HAPPEN TO DRUM PRESSURE
2.WHY ALWAYS RESEAT PRESSURE IN SAFETY VALVE LESS THAN LIFTING PRESSURE.ANY CALCULATION IS THIS FOR.WHAT BASIS SPECIFYING LIFTING PRESSURE.
3.USING SPRAY MEANSWHETHER IT WILL AFFECT HEAT RATE.USING THIS IS GOOD OR NOT
Herman Jul 1, 2010 7:03 PM
The size of pump to reach 80 bar
Sir, i need to know the size of my pump (capasity, etc) to reach 80 bar of pressure on my boiler (220 tph). Thanks
rajapandian Apr 30, 2010 3:03 AM
axial shift in turbine
hi sir,
thanks for ur reply.at what cases at all, axial shift inturbine will go to negative side
johnzactruba Apr 29, 2010 5:17 PM
reply rajapandian
Losses can be put as two types. One that is fixed irrespective of the load. The other is variable with the load.At part loads the fixed losses are proportionately higher. This why the efficiency is lower at part loads.
rajapandian Apr 29, 2010 9:17 AM
efficiency
hello sir,
at part load boiler efficiency is low,may i know what are the reasons for that
johnzactruba Apr 29, 2010 8:58 AM
reply rajapandian
Some of the minor cracks or defects may not show up at 1 times the pressure. Higher pressure will make these defects open up.
rajapandian Apr 28, 2010 10:59 AM
boiler hydrotest
hello sir,
why we have to do boiler hydrotest at 1.5 times of mapressure
kudzai dzapasi Apr 6, 2010 9:51 AM
HPT
i am working on my final year project to design and construct an automated hydrostatic pressure testing electrical pump.i would like to get relevant sources to help me with the literature review with regards to both the manual HPT pumps and electrical HPT pumps.
johnzactruba Apr 5, 2010 6:36 PM
reply imran Khan
Boiler Banks.
in smaller capacity boilers there are two drums , the upper and the lower . These are connected by tubes large no. of tubes. Flue gas passes through these tubes. Evaporataion takes place in these tubes. These are called bank tubes. Check the below link to see the image.
http://tppboilers.com/boilerbanktubes.html
johnzactruba Apr 5, 2010 6:30 PM
reply imran khan
The compressibility of water is only 1.5 to 2 % . The volume is calculated by this.
Running hrs of the pump need not be the correct volume flow. There may be many air pockets in the boiler tubes that are not fully released during the filling. The excess volume is because of filling of this air pockets. The extra time taken also because of this. Vents at all high spots is the only way out.
There is no clearly defined leakage rate. But for the holding time of 30 minutes it should be around 0.1 bar. Pressure loss mainly occurs due to passing and gland leak in valves. There are hundreds of valves and some are connected with pipes in the discharge where passing cannot be identified.
imran khan Apr 5, 2010 7:22 AM
what is boiler Hot Bank ?
sir ,

what is the means of terminology boiler hot bank ? please explain it ?
imran khan Apr 5, 2010 7:21 AM
allowable pr. drop in boiler hydro after holding in
sir ,

After Pressurising the boiler to hold desire ( Test Pr. ) pr. ,but there is a littel drop in pr. even though there is no leakage .
Why these pr. drop occurs ?
and how much allowable pr. drop .?
imran khan Apr 5, 2010 7:16 AM
How to Flush undrainable part
How we can flush the undrainable part like Superheater ?
imran khan Apr 5, 2010 7:14 AM
Is there any formula for calculate the amount of water & pump selection
sir ,

Resently we have performed the internal hydro test , for reference i havecontec to you and found the in practical same data , we have selected a pump of 25 L/min and for emergecny 50 L/min pump also , and after filling the boiler it takes 12 M3 water to reach up to 403 bar , amount of water calculated as per running hrs of pump .

I want ot know any calculation for this available ?
Arun Raja Apr 3, 2010 9:30 PM
Energy manager and auditor
Sir,
I want to know about the role of energy auditor exam which will be conducted by BEE and what r the opportunity please
johnzactruba Mar 31, 2010 9:57 AM
reply Imran Khan
1. You may require 6 to 10 cubic Meter. But the time required to reach the pressure will depend on how effectively the air is released. There should not be any air pockets.
2. A 25 L/min pump will be sufficient for pressurizing
Imran Khan Mar 31, 2010 2:59 AM
amount of Water Requried for Pressirisation after Boiler Filling
sir ,

How much water requried for Pressurisation after complete fill the boiler .

1. I have to pressuried the boiler upto 403 bar , amount of water requried for fill the boiler 639 M3
2. Selection of Piston Pump capacity ?
johnzactruba Mar 22, 2010 10:47 AM
reply maniraj
in addition to chemical dozing nitrogen capping may also m be done fro long term storage .
Maniraj Mar 20, 2010 3:26 AM
Drainable and non drainable hydrotest
Sir,

If the hydrotest is carried out for both drainable and non drainable part at the same time and after hydro test the water will be present in the non drainable part for minimum of 5 to 6 months upto light up is it allowed to do so?
johnzactruba Mar 19, 2010 8:09 PM
reply Maniraj
Due to the physical configuration of the circuit, it may not be able to drain the circuit after the hydro test.
As long as the water has a corrosion inhibitor, holding the water is not a problem.
maniraj Mar 18, 2010 8:39 AM
Drainable and non drainable hydrotest
I know the difference between drainable and non drainable hydro test in high pressure pulvirised boiler.( In india BHEL recommends this two types seperately in the boiler supplied by them)

My question is what is the need for doing so? Is it allowed to carry out directly non drainable hydro test after completing all the welding in boiler?

Kindly explain in detail
johnzactruba Mar 13, 2010 5:55 AM
reply kudzai dzapasi
For low volume tanks / or pipes testing manually is best since you have good control of the pressure. For large volumes high pressure applications electrical pumps have to be used.
kudzai dzapasi Mar 13, 2010 5:09 AM
HPT
what are some of the advantages and disadvantages of manual hydrostatic pressure pumps over electrical ones?
johnzactruba Feb 28, 2010 4:54 PM
Reply GURPREET
At lower temperatures the steel is brittle and has lower strength. It may no be able to withstand the high pressure during the test. This is more releevant in cold countries where the temperatures are very low.
GURPREET Feb 28, 2010 2:28 PM
HYDRAULIC TEST
SIR,
i WANT TO KNOW WHY IT IS WRITTEN IN BHEL MANUALS THAT WATER TEMP MUST BE ABOVE 25 DEG IN ORDER TO CARRY HYDRAULIC TEST OF BOILER
johnzactruba Feb 5, 2010 8:06 AM
reply maniraj
Pressure increase is around 3- 4 bar /min. Practically the increase takes place in steps of 10 or 20 bar and then stabilised at each step.
At 1. 5 times for 30 minutes no drop is allowed.
Maniraj Feb 5, 2010 6:06 AM
RE: What is Boiler Hydrostatic Test?
What should be the rate of increase of pressure during the hydro test? How much pressure drop is allowed during hydro test at the 1.5 times of design pressure?
johnzactruba Dec 23, 2009 8:57 PM
reply Chok
If the pump is rated to greater than the hydrotest pressure this can be used. A positive displacement pump is simpler and easier to achieve the hydro test pressure.
The pressure has to be increased gradually in steps of around 5 bar upto 30 bar hydro test pressure . For increasing the pressure of a 60 m3 tank the water required is less than 0.6 m3 in 10 minutes operation of the pump. A 60 litre per min pump is sufficient. Important is the pressure capacity of the pump.
Chok Dec 23, 2009 4:15 AM
Hydrostatic press test
for a press test of only 20bar in a vessel of 60m3, a) could i propose vertical in line pump instead of piston pump ?
b) after filling up the vessel, what is capacity of high pressue jet pump should I size in order to bring the pressure from atm pressure to 20 bar?
johnzactruba Dec 14, 2009 4:46 AM
reply - sairam
Hydro test using water is the safest and simplest way.
Another method is using compressed air. Normally hydro-tests of large boilers are preceded by a compressed air test usually at 1 to 2 bar pressure. Higher pressures are not safe. This test will indicate ,big leaks like unfinished welds, open valves etc. Filling and releasing is simple and not messy like water.
In instrumentation and oil lines where ater cannot be used , Nitrogen is used. Maximum pressures that can be used depend on the Nitrogen Cylinder pressure available.
johnzactruba Dec 14, 2009 4:46 AM
reply - sairam
Hydro test using water is the safest and simplest way.
Another method is using compressed air. Normally hydro-tests of large boilers are preceded by a compressed air test usually at 1 to 2 bar pressure. Higher pressures are not safe. This test will indicate ,big leaks like unfinished welds, open valves etc. Filling and releasing is simmple and not messy like water.
In instrumentation and oil lines where ater cannot be used , Nitrogen is used. Maximum pressures that can be used depend on the Nitrogen Cylinder pressure available.
sairam Dec 13, 2009 12:01 AM
RE: What is Boiler Hydrostatic Test?
can u tell me the hydro test in boiler headers and is there any alternative apart from hydro test to check the pressure inside the boiler headers
johnzactruba Nov 26, 2009 5:45 PM
Jinasiri Samarakoon
Safety valves are tested by firing and operating the boiler slowly increasing the pressure till the safety valve set pressure is reached.
If many safety valves are there only one is tested the others are gagged.
Another method is to use a hydraulic device that without the boiler actually reaching the set pressure. The boiler is operated at a pressure less than the set pressure . The device provides the extar pressure for testing to the rated values.
This saves the boiler from being unnecessarily stressed.
Jinasiri Samarakoon Nov 25, 2009 11:17 PM
Testing Safety valves of Boilers
Would you pl. explain how to test a safety valve of a boiler.
Thanks & B.Regds.
johnzactruba Oct 14, 2009 11:25 PM
reply jay bhadja--safety of thermal power plant
johnzactruba Oct 14, 2009 10:45 PM
reply to Nelson- pump
To calculate the size of a pump you should know
1. what is the quantity of liquid to be pumped litre/ sec
2. What is pump head required or the pressure.
Thi s depends on how your process is configureed, your pipie sizes etc.

Tha same holds good for piping sizing also.
Nelson Oct 14, 2009 10:51 AM
pump
i need to know the size of my pump and the motor that is going to drive the pump to pump 50000 unit of soft drink per day and to work 8 hours a day
jay bhadja Sep 16, 2009 7:18 AM
safety of thermal power plant
i want the safety related to the the thermal -power plant
 
blog comments powered by Disqus
Email to a friend