At the center of the project is the Mubarak Pumping Station which cost $436 million to build and which was completed in March 2005. It

click to enlarge
is located in the center of the lake and is completely surrounded by water.
It has 24 vertical pumps which are installed in two parallel lines along both sides of the station. The pumps are load-controlled and have adjustable speed settings. At any one time, only 18 of the pumps are running. Three are used for maintenance needs, and three are kept in reserve. The station, with an open 50 meter deep intake channel, the deepest inland channel of its kind, will make the complex able to pump 1.2 million cubic meters of water per hour. The canal channel is about 30 meters wide, being dug out of rock and sand. The channel is called the Sheikh named after Sheikh Zayed al Nahyan, President of the United Arab Emirates (UAE). UAE is financially backing this project, which means financially the project has all the support one can imagine.
This accomplishment in itself is impressive. However, the Mubarak Pumping Station is praised by civil and mechanical engineers for two other, less obvious, reasons. First of all, the structural system that supports the station is made up of steel mini-piles, which are cost-effective and earthquake resistant. Traditional concrete piles would have been very expensive to use in this location. The steel mini-piles are installed at the base of the pumping station. They connect the station to a foundation raft. With this construction, the piles are free to tense against any seismic movement. They also offer some resistance to shearing forces.
Secondly, the underwater areas of the station use a jointless design. This design means that the structure is watertight even at a temperature range from 0 to 50 degrees C. Joints are only used above the normal high water level of the lake. Because of these two engineering achievements, the Mubarak Pumping Station was recognized, when it was completed in 2005, by the American Society of Civil Engineers as one of the five most outstanding civil engineering achievements of the year.
The Mubarak Pumping Station was sponsored by the Government of Egypt’s Ministry of Water Resources and Irrigation. The design of the station was completed as a joint venture project between Hamza Associates and Lahmeyer. Finally, the construction of the station was completed by Arabian International, Skanska, and Hitachi.
The Toshka Project, with the Mubarak Pumping Station in particular, is truly an engineering wonder that, when complete, will better the lives of millions of people. Long-term, the project is planned to allow Egypt to meet all of its own food requirements in addition to providing agricultural exports.